Project Details
Client
Building Owners
Location
130 Stirling Street, Perth WA 6000
Year Completed
2021
Category
Façade Systems
Project Overview
Kilmore Group was engaged to undertake the full recladding of the non-compliant ACP panels. The building consisted of approximately 2850m2. Half was replaced with non-combustible panels of a similar appearance to the originals while the other half was replaced with a Colorbond material, offering the client significant cost savings.
Works Included:
- complete façade removal and replacement
- value engineering options
- cranage, traffic control and obstruction permit obtainment
- scaffolding
- HSEQ management
- noise and dust mitigation
- electrical service work maintenance
- internal works as per a staging methodology
- stakeholder management and communication.
Similar Projects
View some similar projects below